The Ultimate Guide to RIBA’s Process for Architects [Infographic]
The Work of Plan constructed by the Royal Institute for British Architects has become an unwritten industry standard.
Not just British Architects rely on the 8 phase design and construction plan.
Whether you are new to the concept or looking to refresh your RIBA knowledge here is the Ultimate Guide for you!
What is RIBA?

The RIBA is the Royal Institute for British Architects who developed the first plan of work back in 1963.
The aim of the plan was to provide an outline model for the building design and construction process in the UK.
For half a decade the plan has consistently been adapted to changes in the industry until it got completely revised in 2013.
The new plan of work is set to be the updated standard of procedure.
8 detailed phases lay out the path from initiation of a project all the way to the completion of a building and ribbon cutting.
The revised plan further includes a phase dealing with the occupied building and maintenance.

The phases are
- 0 – Strategic definition. (New addition)
- 1 – Preparation and brief.
- 2 – Concept design.
- 3 – Developed design.
- 4 – Technical design.
- 5 – Construction.
- 6 – Handover and close out.
- 7 – In use. (New addition)
The phases are categorized in 5 areas of the project:
- The new additions are both pre and post areas.
- Phase 1 is Preparation.
- Phase 2, 3 and part of Phase 4 are Design stages
- Remaining of Phase 4 is Pre-construction
- Phase 5 is Construction
- Phase 6 is Use
No architect is forced to follow the rules set out by RIBA, although it has become a universal standard.
This guide will explain the most recent Plan of Work and provide a detailed explanation of each step.
What changed?

One of the significant changes in the 2013 model is that it aligns to more than just the traditional procurement route.
While the majority of architects still use the traditional contractual agreements other sorts, like the Design and Build forms of procedure have also grown in popularity.
The new WoP is flexible to fit the new trends in the industry.
On the website of the RIBA it is possible to create a custom work of plan to fit the desired procurement route.
The 2007 RIBA’S Plan of Work consisted of 11 steps lettered from A to L.
The 2013 RIBA’S Plan of Work is divided into 8 stages numbered 0-7, to avoid confusion to the previous phases.
Adapting to the changes in the industry, the new phases are also BIM ready, mapping out the processes.
If you are unfamiliar with BIM, there are helpful videos explaining the process.
The Plan of Work introduces a new flexibility when it comes to (Town)-planning.
The 2013 recognized the need to make a plan adaptable to different sizes and scopes of projects to ensure the best experience for both ends of the contract.
Through adjustable templates their website, the plan can be completely fitted to the scale of the project.

The tasks marked *Variable can be adjusted to the 3 P’s Procurement, Programme and Planning.
The 8 Phases
To demonstrate the process of construction through a real life example, we will show the project Fountainbridge by Oberlanders Architects in Edinburgh.
The project started in 2006 and has won multiple design awards since opening in 2012.
Some examples for the design process are not publicly available and will be shown through other project.
0 – Strategic Definition

One of the new additions to the 2013 Plan of Work is the first step of the cycle.
During the strategic definition it is the suppliers goal to properly consider the clients Business Case and Strategic Brief, before creating the Initial Project Brief in Phase 1.
A Business Case is the client’s rationale behind the initiation of a new building project.
This can be anything from a simple spoken request, to a detailed written proposal, explaining what exactly they want from this project.
The architect is to thoroughly go through the wishes and intentions of the client before they can work on the Project Brief.
Together they are able to properly define the scope of the project and go into the preparation process more prepared.
The business case often includes first cost evaluations and discussing the sites available for the project. This phase is particularly important in terms of sustainability, for example if it would benefit for a building to undergo refurbishment rather than be built new.
An example of a new refurbishment boom are first-tier cities in China.
There, no more land is being released for development, driving the industry towards refurbishment of old building instead.
Factors influencing this can be aspects like budget, local planning policies and building context.
Initial considerations of all team members for the projects are being considered, to create the best work force possible.
The Project Program is also being established.
This outlines the projected length of the project and how briefing, design and construction phases are going to be distributed in this time frame.
The only people involved at this stage are the client and the architect.
No information exchange with the government is necessary yet.
Summary Phase 0:
- ensure the client’s Business Case and the Strategic Brief have been properly considered
- establishment of Project Plan
- consideration of Team Members
1 – Preparation and Brief

The main goal of the second stage, or Phase 1 (not to get confused) is to produce the Project Initiation Document (PID)
The PID includes the Initial Project Brief and a Feasibility Report, as well as the Client Brief and Business Case from the previous phase.
The PID is what is being used to gain funding for feasibility studies.
This stage is important to ensure that the Concept design in Phase 2 can be as productive as possible.
1.1 Objectives
The Initial Project Brief lays out the main Project Objectives, such as:
- Quality Objectives
- Project Outcomes
- Sustainability Aspirations
- Project Budget
- Other parameters/ Constraints
The quality objectives are the objectives that set out the quality aspects of the project.
Size and location of the project are defined
The demanded project outcomes have been discussed in the first stage.
How long it takes to produce the PID fully depends on the scope of the project and special requests that need to be considered.
Depending on the project it can be relevant to contact local authorities pre-appointment.This will make future engagement easier and help guide the design from early on.
Local architect should be contacted to get familiar with local policies.
Who’s in charge of creating the project team depends on the contract between architect and client.
1.2 Contract
The relationship is established as a Contractual Tree:
- Client Service Consultancy: (Full Control)
- Here the architect does everything
-Landscape - -Interior designer
- -MEP (Mechanical, electrical, plumbing)
- Here the architect does everything
- Client Consultancy: (Full service)
- The client does everything in terms of hiring all subcontractors
- -Architect only responsible for design part
- Split Consultancy: (Shared partnership of a project)
- The Architecture firm works together with Financial establishment/government/engineering company
- -Usually chosen for larger projects
- Sub-Consultancy: (Very specific)
- Focus on one element of the project
- -This can be doing just landscape, interior design, drawings, design, etc
- -Client chooses what role the architect will play in the project
It is required to create an initial Risk Assessment.
Once the Initial Project Brief and Feasibility Report have been completed the Project Initiation Document is finished and the project can move into the design phases. (2 – 4)

Summary Phase 1:
- creation of Initial Project Brief
- creation of Feasibility Report
- production of Product Initiation Document
- assembling the Project Team
- creation of Risk Assessment
2 – Concept Design

The project is now in the first of 3 design phases.
The goal of this phase is to produce a Final Concept Design.
2.1 First drafts
This is the first time the client gets to see a visual representation made from the Project Brief.
The visual can be anything from drawings to models designed to show the aesthetics of the project including:
- -interior
- -exterior
- -landscapes
General procedure is that the client receives 3 different concept proposals for the construction.
They can be similar or completely different.

The client then gets to choose which proposal fits their needs the best by combining elements from all designs.
2.2 Final Concept Design
When the final design has been agreed on the architects begin with the design.
This includes for example:
- -general drawings
- -sketches, drawings
- -models (physical + 3D models)
- -very rough renders.
The drawings should be 1 to 50/500 (Adjustable to project needs)

For example:
Part of the drawings are:
- -What is surrounding the project on the plot of land
- -How does the external world affect the design
For example:
- -busy highway,
- -river,
- -parking lots,
- -foot traffic etc
Large scale drawings are helpful in seeing how a building is going to function in its location.
It is essential to revisit the brief during this stage and it should be updated and issued as the Final Project Brief as part of the Information Exchange at the end of Stage 2.
2.3 Hand In
The final design has to be prepared for hand in to the client.
This includes:
- General plans
- sections, elevations
- all relevant material to express the design.
The drawings move up to a scale of 1 to 100/200

Concept Design Checklist
Plans:
Tells you how your designs to the surroundings.
Provides other information such as square meters, walls, size of plot, relation of what is indoor and outdoor.
For Example:


Elevations:
Prodive the vertical visual aesthetic of your design
-It’s the exterior shell, the view from the outside
For example:


Renders
Future drawing (the design in context of what it would look like once it’s build)
-3D mock up
- 1 render of the building
- 1 render of the interior
- 1 render of how it relates to the landscape and surroundings
1 render of the building in colour:


1 render of the interior:
1 render of how it relates to the landscape and surroundings:



Situation plan:
What’s around it (access to it)
1 to 1500 to 1 to 5,000 (Adjustable to project needs)
-View from above showing the land around it

The following types of design were not available from Oberlanders Architects and are shown by other project examples:
Sections:
Provide you with the vertical elements of the building
- Gives you a good idea of how your design and your building relates to other buildings heightwise
For example:

Axonometrics
Technical 3D View of the design for the entire building Visualization of a plan
For Example:

Physical models
Can be any size, helps demonstrate the final product in a more tangible way

In the past years using Virtual Reality has been introduced as a way to show clients the designs in 3D.
This might set of properly once the technology further advances.
2.4 Permits and permissions:
Local planning authorities need to be consulted to obtain permits and permissions needed.
Things to consider are:
- The historical significance of the site
- Government issued building programme
- The surroundings (Water, land (brown and urbanized))
- Height
- Need air rights?
Feedback from the consultations may result in changes to the design.
The length of Phase 2 is depending on the scale and complexity of the project
2.5 Cost Plan
With the finished design the elemental cost plan for the project can be produced. This lays out all assumptions, abnormal costs and whole-life costs.
Summary Phase 2:
- Produce Initial Concept Design
- Client decides on Final Concept Design
- Creation of visualisation of Project Brief
- Plans
- Sections
- Elevations
- Axonometrics
- Renders
- Creation of Elemental Cost plan
3 – Developed Design

The main goals of this phase are to produce a Final Design to be send to authorities and approved.
The architectural, building services and structural engineering designs will be finished by the end of phase 3.
With the Final design approved the Cost plan can be determined and aligned to the Project Budget.
It usually involved the planning application, but due to the flexibility of the 2013 PoW, it can vary across the phases.
In phase 3 the design is further developed.
Visualisations are moved to a 1 to 20/50 scale depending on the project scale.
The designs produced now are dimensionally correct and co-ordinated as CAD-drawings.
Models should show:
- -Window, door, exit, fire escapes, stairway locations
- -Wall patterns
- -Materials
- -Some electrical
- -Fittings, fixtures, equipment
- -Environmental and cleanup fees/charges
- -Atmospheric conditions (Mood boards/Material boards – e.g. concrete and wood, glass and tiles, etc)
- -Load bearing mechanical (structural logic of the building – e.g. foundation, pillars, and load bearing walls)
- -Aesthetics from the interior, exterior, and landscapes
Building System Services:
- -Tech, security, advanced functionality
- -Mechanical, Plumbing, Electrical (MPE)
- -Green/eco/solar
Structure of the Building – Type Selection
- -Concrete (prefab + in situ)
- -Masonry (brick + mortar)
- -Steel (i beams + cladding – multiple types)
Changes during this phase are usually documented.
The chosen materials and dimensions can give an accurate estimate of the cost plan.
Changes in this phase are often made to adjust to the project budget.
The cost estimation is where things tend to go wrong.
Avoid these common errors for the closest estimate possible:
- Lack of transparency
- Not using an estimating checklist
- Oversimplifying Labour costs
- Ignoring weaknesses
- Lack of risk estimation
- Number errors
Phase 3 is usually when the planning application is being submitted to the responsible authorities.
The detailed drawings and reports are to be included in the application.
A planning application can include:
- A standard application form
- Location plan, showing the site and context
- Site plan or block plan, showing the proposal in greater detail
- An ownership certificate
- Agricultural holdings certificate
- Application fee
Further factors depend on location and scale of the project.
Summary Phase 3:
- Final Design approved
- Submission of Planning Application
- Cost plan finished (Labour excluded)
- Creation of detailed CAD models
4 – Technical Design

The goal of Phase 4 is to prepare the detailed technical designs for the building.
In the end of the stage the designs should include all architectural, structural and building services information.
This includes any design for specialist subcontractors and specifications.
All designs are to align with the Design programme and Design Responsibility Matrix.
4.1 Detailed Drawing
The Lead and Construction architect come together to produce detailed drawings of the designs.
The scale of detail now goes from 1 to 1 up to 1 to 20.

How detailed each designer has to get depends on whether the construction will be built according to the design team or based on information given by a specialist subcontractor.
The drawings now include things like electrical outputs, insulation and other specifics.
Depending on the project, all needed engineers are subcontracted and work alongside the Lead and Construction architects.
At this stage the overall design of the building does not change anymore.
The Design team is expected to work on their part individually, according to the designs set out in the previous stages.
It is possible that the design team has to respond to queries that arise during the construction phase.
Once the detailed designs are finished the Architects hand it over to the Project Manager.
It is important to regularly check in with the authorities during this phase.
4.2 Tender
If the supplier has already been chosen it is their responsibility to create their own supply chain.
For this they have to prepare tender documentation and their own version of the employer’s information requirements.
If the supplier hasn’t been chosen the tender documentation and pre-tender estimate now have to be produced in order to tender the construction contract.
4.3 Contractors
All contractors are reviews, new ones are chosen, approved and contracted out.
Who is responsible for appointing all subcontractors depends on the original contract between Architect and Client.
The Lead architect and Project manager approve all selections of contractors and discuss these with the client for his approval.
Summary Phase 4:
- Preparation of detailed drawings
- Designs by specialists subcontractors
- Construction Architects join the team
- Preparation of tender documentation
- All contractors approved by Project managers and client
5 – Construction

The goal of phase 5 is the offsite manufacturing and onsite construction of the building.
All construction is according to the designs produced in the previous stages.
The Design Team still has to respond to design queries arising during this stage.
5.1 Construction and Building

The Architect’s role during construction depends on the contract.
Traditionally the client appoints the contractor who is responsible for the work onsite.
The architect firm usually offers a Contract administration service to oversee that the work is according to the programme through regular visits.
The contract administrator deals with:
- Tendering
- Requesting/ Issuing instructions from the client
- Construction progress reports
- Reporting defects
- Issuing interim certificates
- Documenting defects and issuing making good certificates of said defects
- Issuing the final certificate

5.2 Health and Safety
Local inspectors review and observe the site to make sure all health and safety laws are being followed
Summary Phase 5:
- The Construction onsite
- Manufacturing offsite
- Processing Design Queries
- Contract Administration Service
- Issuing Final Certificate
6 – Handover and Closeout

The goal of phase 6 is the handover of the completed building and the conclusion of the building contract.
The client is now able to occupy the building.
For 6 to 12 months, also called Defect Liability Period, the contractor is still responsible for any defects on the property.
6.1 Report
At the end of construction, a report is produced covering the contractors, errors, accidents, incidents of waste/loss.
The contract administrator is issuing his final report on the construction.
In some cases the client may keep a retention sum for the contractor unit the Defect Liability Period is over. This ensures that the contractor does his job.
6.2 Inauguration and official opening
The completed site is visited by the client and other relevant parties.
All members of the Project Team are invited and the building is officially ‘In-Use’.
Often includes an official Red Ribbon Cutting ceremony and champagne.

Summary Phase 6:
- Completion of construction
- Hand over to client
- Issuing of final report
- Start of Defect Liability Period
- Champagne
7 – In Use

This is the second new addition to the RIBA’s Plan of Work 2013, and aims to provide an aftercare service to the client and the building.
The service provided to the client can include for example:
- Advice on Maintenance
- Energy certificates or consumption
- Letting or tenants queries
- General
- management of facilities
- Insurance
- Tenants queries
- Facilities management
- The preparation of tender documents for maintenance and operation contracts
Sometimes it’s necessary to pass on expert knowledge in order for the building to be used properly.
This especially applies when it comes to sustainability.
The ‘end of life’ of a building can be part of Phase 7 or considered part of the Phase 0 of a new construction cycle.
In this case it’s considered whether the development can be reused by refurbishing it or has to be demolished.
This stage is what united the phases of the plan into a cycle of development.
Phase 7 Summary:
- Aftercare service for client
- Advice on ideal use of property
- Sustainability
- Consideration of end of life
RIBA Plan of Work Concluded
The Plan of Work is recognised internationally as standard procedure.
While no one is expected to use it, by doing so you can play it safe.
“Unless they are inappropriate, use the RIBA forms of Appointment” – A Guide to Keeping out of Trouble.
The guide allows to simplify the project to both architects and clients, and increases the communication between both parties.
Need help getting started?
We worked through the red tape and bureaucracy so you don’t have to.
In most cases you must complete some official forms for the Building and Residency Register (BBR forms) together with the building application for the municipality.
Visit your municipality’s website and find the correct forms to be filled in. Here, and at BBR.dk , you can also read more about the review and application for construction work.
- Are you looking for existing building drawings?
- Local authority contact?
- No sure what you can or cannot build? See the restriction here.
- Building regulations to consider?
- Help with your Cost estimate?
Download our full infographic! High-quality!
Get started on RIBA with the right tools and process in place! Explore our list of 140+ architect tools that can make your work easier and save bunch of time!
What do you think about the RIBA Plan of Work 2013? Share your experience and thoughts, send us a message!
Leave a Reply